Harbor Road Update
Construction Plans (90% Complete)Submitted to NYS Department of Environmental Conservation on September 22nd, 2026.Permitting process has begun.
Stony Brook, New York
(631) 751-2244
Construction Plans (90% Complete)Submitted to NYS Department of Environmental Conservation on September 22nd, 2026.Permitting process has begun.
Update as of August 2026: Immediately after questions of ownership arose, The Ward Melville Heritage Organization (WMHO) took action at its own expense to complete critical studies needed for repair

On behalf of the Ward Melville Heritage Organization and the community, we thank her very much. Thanks to her, the project will get done.

Congressman Nick LaLota presents a $5 million check to Brookhaven Town Supervisor Dan Panico, alongside Highway Superintendent Dan Losquadro and Councilmember Jonathan Kornreich, marking the federal funding secured to restore